MILLIKEN 115 KV SUBSTATION: 50 MW LOAD INTERCONNECTION & INFRASTRUCTURE OPTIMIZATION
  • High-Impact Load Integration: Integrating a new 50 MW load into Avangrid’s 115 kV transmission system required precise substation modifications to uphold reliability and meet growing demand.

  • Legacy Asset Repurposing: Relocating the Cayuga GSU transformer feeder posed technical and spatial challenges within existing infrastructure constraints.

  • Operational  Segmentation:  Maintaining functional independence between customer and utility necessitated meticulous  meticulous separation in alignment with utility ownership protocols.

  • Strict Regulatory Compliance: The project demanded adherence to a complex matrix of standards—NERC, NPCC, NYSRC, NYISO, and NYSEG—through rigorous studies and infrastructure validations.

  • Detailed System Studies: DST performed detailed thermal, voltage, stability, and load flow assessments of the Milliken substation and Cayuga’s 115 kV systems.
  • Substation Infrastructure Upgrades: Identified and designed high-side equipment modifications to accommodate the repurposed GSU transformer and ensure compatibility with the load’s dynamic profile.
  • Protection & SCADA Enhancements: Evaluated existing protection schemes and   developed   relay,   SCADA,   and   communications   upgrade   plans   in coordination with NYSEG and Avangrid standards.
  • Metering Reconfiguration: Proposed metering system redesigns for compliance, accuracy, and seamless integration with utility-owned metering architecture.
  • Asset Demarcation Strategy: Designed and documented a separation plan for shared facilities, ensuring clear operational boundaries and eliminating system interdependencies.
  • Structured Deliverable Rollout: Delivered a phased engineering package culminating in a PE-stamped Final Facility Study Report with detailed technical, financial, and compliance insights.
  • Compliance-Centric Engineering: Delivered a technically robust and   regulation-ready  solution,  ensuring  full  alignment  with regional grid codes and interconnection mandates.
  • Tailored Technical Execution: Customized engineering based on substation-specific constraints and the 50 MW load’s operational flexibility, including DSM compatibility.
  • Cost-Effective Infrastructure Utilization: Optimized existing assets for reuse, minimizing capital costs while enhancing system resilience and performance.

 

  • DST provided data, maps, charts, and calculations in a format easily accessible by ComEd.
  • DST successfully identified necessary grid upgrades and provided cost estimates for DER integration.
  • Throughout this program, DST ensured smooth communication and documentation, meeting regulatory and technical requirements for DER interconnection.