IKE- POLEFOREMAN SUPPORT SERVICES
  • Managing the complexity of accurately modeling a high volume of
    utility poles, 409 locations across two primary work orders to meet strict client and regulatory standards.
  • Ensuring all designs and clearances for hundreds of distinct assets were fully compliant with PPL’s specific engineering requirements and NESC standards.
  • Overcoming potential data accessibility issues to perform comprehensive modeling at scale without requiring extensive, costly field verification.
  • Delivering a large quantity of precise models and reports within project timelines to support efficient project execution.
  • Executed complete pole modeling for 409 locations using the
    specialized IKE Pole Foreman software.
  • Leveraged provided access to ENTRUST/PPL’s databases to retrieve
    all necessary pole, circuit, and system data for modeling accuracy across the entire project scope.
  • Applied deep expertise in utility standards to input accurate design
    parameters and perform rigorous clearance verification for each of the 409 poles.
  • Utilized our own Pole Foreman license to ensure a seamless,
    uninterrupted project workflow and data security throughout the engagement.
  • Delivered 409 fully completed and compliant IKE Pole
    Foreman models, providing a reliable digital twin for engineering analysis and a clear record of work.
  • Provided PDF reports for all 409 modeled poles, offering
    clear, auditable documentation of design details and
    clearance verification.
  • Ensured 100% compliance with PPL standards across all
    delivered assets, mitigating risk and ensuring project
    approvals.
  • Demonstrated scalability and reliability by successfully
    managing and delivering a significant volume of models,
    establishing a proven track record for large-scale projects.
  • Enhanced project efficiency by delivering accurate, timely
    data that accelerated downstream engineering and
    construction phases for both work orders.
  • DST provided data, maps, charts, and calculations in a format easily accessible by ComEd.
  • DST successfully identified necessary grid upgrades and provided cost estimates for DER integration.
  • Throughout this program, DST ensured smooth communication and documentation, meeting regulatory and technical requirements for DER interconnection.