Installation Of ARGA Battery Monitoring System - MILFORD Substation
  • Integration of an Arga Battery Monitoring System into an existing, space-constrained substation control house.
  • Limited DC circuit capacity requiring a new DC distribution panel.
  • Need for reliable communication between Arga Monitor and Orion
    RTU.
  • Coordination required across multiple DPL teams (SME, EM,
    Protection).
  • Parallel Spare Transformer project by Worley sharing DC infrastructure, creating interface and documentation risks.
  • Performed site assessment to validate annunciator space, battery layout, and cable routing.
  • Coordinated with DPL teams to confirm equipment, alarms, I/O, and communication requirements.
  • Developed full engineering design including one-lines, wiring diagrams, terminal plans, and cut-in/cut-out packages.
  • Engineered serial communication using SEL-2886 RS-232 to RS-485 interface to Orion RTU.
  • Designed a new standard DC distribution panel, including sub-feed
    integration and control house layout updates.
  • Engineered cable routing from battery terminals to annunciator panel
    per DPL standards.
  • Coordinated documentation and interfaces with Worley’s parallel
    transformer project.
  • Delivered phased 60%, 90%, IFC, and close-out engineering
    packages.
  • Identified and resolved DC capacity limitations before construction, reducing field risk.
  • Delivered a fully coordinated, constructible design aligned with DPL standards.
  • Enabled seamless integration across monitoring, DC
    power, and SCADA systems.
  • Prevented conflicts between parallel projects through
    proactive cross-team coordination.
  • Provided clear, field-ready documentation supporting safe installation and commissioning.
  • DST provided data, maps, charts, and calculations in a format easily accessible by ComEd.
  • DST successfully identified necessary grid upgrades and provided cost estimates for DER integration.
  • Throughout this program, DST ensured smooth communication and documentation, meeting regulatory and technical requirements for DER interconnection.