Skip to content
Home
About
Services
Distribution Engineering
Substation Engineering
Transmission Engineering
Project Management & Controls
Photovoltaic (PV) Engineering
Field Services
News
Projects
Careers
Home
About
Services
Distribution Engineering
Substation Engineering
Transmission Engineering
Project Management & Controls
Photovoltaic (PV) Engineering
Field Services
News
Projects
Careers
Contact Us
Home
About
Services
Distribution Engineering
Substation Engineering
Transmission Engineering
Project Management & Controls
Photovoltaic (PV) Engineering
Field Services
News
Projects
Careers
Hamburger Toggle Menu
info@dstengineers.com
1 (872) 588-4230
Linkedin
whatsapp
IESCO Hosting Capacity & Challenge Action PV Impact Studies
Project Location:
Islamabad, Pakistan
DST Team Leader:
Razzaq Kamboh
Challenge
Data gathering from multiple IESCO Data sheets
Validation of inconsistent or incomplete datasets
Installed PV capacity records lacked associated transformer
numbers
Cleaning and Placement of Existing PV into the Synergi model for accurate analysis
A custom methodology was developed, as no prior hosting capacity and der impact study were conducted in Pakistan before DST’s involvement.
Action
DST collected and verified data across IESCO feeders.
Synergi analysis was performed to assess PV impact.
Continuous coordination was maintained with the IESCO technical team to ensure alignment.
KPIs were implemented to measure communication effectiveness
and track progress.
DST team refined the study framework to suit Pakistan’s grid
characteristics.
DST Value Addition
DST pioneered the first hosting capacity and PV impact study in Pakistan.
The team provided clean models, validated datasets, and technical insights to support planning decisions.
Findings helped IESCO understand grid limitations and integration potential for DERs.
DST facilitated smoother collaboration between planning and operations teams.
The study laid the groundwork for future DER integration strategies across the region.
DST Value Addition
DST provided data, maps, charts, and calculations in a format easily accessible by ComEd.
DST successfully identified necessary grid upgrades and provided cost estimates for DER integration.
Throughout this program, DST ensured smooth communication and documentation, meeting regulatory and technical requirements for DER interconnection.